ONSHORE WIND Β· MISO

Onshore wind project J3995, Jasper County

Onshore wind project J3995, Jasper County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Jasper County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2025 (completed)
  2. Withdrawn / abandonedJan 2026 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3995
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
7CASEY - 7NEWTON 345.0kV
Location
Jasper County, Illinois
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
23 April 2025
Proposed online date
July 2030
Withdrawn
January 2026

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem