United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in ISO-NE (New England) (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| New Scotland BESS (NYISO-C24-045) Battery storage |
1,350 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
1,275 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
1,275 MW | Withdrawn / abandoned |
| Offshore Wind Offshore wind |
1,200 MW | Withdrawn / abandoned |
| Dover NY BESS (NYISO-C24-316) Battery storage |
1,000 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
415 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
408 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
366 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
313 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
254 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
251 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
238 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
205 MW | Withdrawn / abandoned |
| Wind Onshore wind |
197 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
166 MW | Withdrawn / abandoned |
| Solar Solar |
165 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
142 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
142 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
135 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
134 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
133 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
125 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
116 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
115 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
110 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
108 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
105 MW | Withdrawn / abandoned |
| Battery Storage addition(QP1192) Solar + storage |
101 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
101 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
101 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
101 MW | Withdrawn / abandoned |
| Battery Storage + Solar Solar + storage |
101 MW | Withdrawn / abandoned |
| Zenobe Rotterdam LLC (NYISO-C24-191) Battery storage |
100 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
93.2 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
81.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
76.0 MW | Withdrawn / abandoned |
| Solar Solar |
68.0 MW | Withdrawn / abandoned |
| Chazy Lake BESS (NYISO-C24-308) Battery storage |
50.0 MW | Withdrawn / abandoned |
| Wood River Substation - Western RI DER Study #3 Solar |
49.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
45.3 MW | Withdrawn / abandoned |
| Solar Increase Solar |
25.0 MW | Withdrawn / abandoned |
| Kent County Substation - Western RI DER Study #3 Solar |
21.7 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)411 Β· 78.5 GW
- NYISO (New York)294 Β· 63.3 GW
- West (non-ISO utilities)237 Β· 46.1 GW
- Southeast (non-ISO utilities)195 Β· 32.8 GW
- ISO-NE (New England)97 Β· 13.2 GW
- ERCOT (Texas)50 Β· 10.0 GW
- SPP (Southwest Power Pool)29 Β· 7,503 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)