BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 101 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Franklin County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1545
Grid region
ISO-NE (New England)
Connection point (POI)
MA_WMECO 115 kV Erving Substation Bus No. 116107
Location
Franklin County, Massachusetts
Technology
Battery: 101 MW
Total requested
101 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
30 May 2024
Proposed online date
August 2028
Withdrawn
October 2025

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem