πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Massachusetts

OTHER Β· ISO-NE

Biomass Project

Biomass Project is a 49.7 MW other request withdrawn in the ISO-NE interconnection queue, in Franklin County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2008 (completed)
  2. Withdrawn / abandonedJun 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
282
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV line near Montage or Fench King substations
Location
Franklin County, Massachusetts
Technology
Other: 49.7 MW
Total requested
49.7 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
15 October 2008
Proposed online date
February 2014
Withdrawn
June 2011

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem