United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 116 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2024 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1499
Grid region
ISO-NE (New England)
Connection point (POI)
Palmer 503 Substation new 115 kV line
Location
Hampden County, Massachusetts
Technology
Battery: 116 MW
Total requested
116 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
13 February 2024
Proposed online date
October 2026
Withdrawn
June 2025

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem