BATTERY STORAGE · ISO-NE

Zenobe Rotterdam LLC (NYISO-C24-191)

Zenobe Rotterdam LLC (NYISO-C24-191) is a 100 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Schenectady County, New York.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1598
Grid region
ISO-NE (New England)
Connection point (POI)
NYISO Rotterdam 115 kV
Location
Schenectady County, New York
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 December 2024
Proposed online date
June 2028
Withdrawn
December 2025

Location

Marker shows the centre of Schenectady County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Schenectady County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem