United States › Grid › Interconnection queues › New York
ONSHORE WIND · NYISOGateway Wind Energy
Gateway Wind Energy is a 79.2 MW onshore wind request withdrawn in the NYISO interconnection queue, in Schenectady County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2008 (completed)
- Withdrawn / abandonedApr 2009 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 312
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- RP Wind NY, LLC
- Connection point (POI)
- Princetown - Rotterdam
- Location
- Schenectady County, New York
- Technology
- Wind: 79.2 MW
- Total requested
- 79.2 MW
- Queue status
- Withdrawn
- Entered queue
- 25 September 2008
- Withdrawn
- April 2009
Location
Marker shows the centre of Schenectady County; the queue data does not give exact sites.
Other requests in Schenectady County
- Glenville Energy ParkGas · 540 MW · withdrawn
- Zenobe Rotterdam LLC (NYISO-C24-191)Battery storage · 100 MW · withdrawn
- Zenobe Rotterdam LLCBattery storage · 100 MW · withdrawn
- ELP Rotterdam SolarSolar + storage · 35.0 MW · withdrawn
- 18405 Scotch RidgeSolar · 20.0 MW · withdrawn
- Johnstown SolarSolar · 20.0 MW · withdrawn
- Scotia Industrial ParkBattery storage · 20.0 MW · withdrawn
- ELP Rotterdam SolarSolar · 20.0 MW · withdrawn
- SII Rotterdam JunctionOther · 9.3 MW · withdrawn
- Mariaville 2 SolarSolar · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem