Glenville Energy Park

Glenville Energy Park is a 540 MW gas request withdrawn in the NYISO interconnection queue, in Schenectady County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 1999 (completed)
  2. Withdrawn / abandonedJul 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
33
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Glenville Energy Park, LLC
Connection point (POI)
Rotterdam 230kV
Location
Schenectady County, New York
Technology
Gas: 540 MW
Total requested
540 MW
Queue status
Withdrawn
Entered queue
30 November 1999
Withdrawn
July 2008

Location

Marker shows the centre of Schenectady County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Schenectady County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem