BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 81.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Bristol County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2024 (completed)
  2. Withdrawn / abandonedSep 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1565
Grid region
ISO-NE (New England)
Connection point (POI)
Interconnect at the 115kV Sykes Rd Substation owned by MA_NGRID.
Location
Bristol County, Massachusetts
Technology
Battery: 81.0 MW
Total requested
81.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
10 June 2024
Proposed online date
January 2027
Withdrawn
September 2024

Location

Marker shows the centre of Bristol County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Bristol County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem