SOLAR + STORAGE · ISO-NE

Battery Storage addition(QP1192)

Battery Storage addition(QP1192) is a 101 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1496
Grid region
ISO-NE (New England)
Connection point (POI)
To interconnect at the POI of Broadleaf Storage, via a shared facility. It is connected as a tap at existing 345 kV line between N. Bloomfield to Agawam Line. POI is approximately 3.6 mi north of N. B
Location
Hartford County, Connecticut
Technology
Solar: 101 MW · Battery
Total requested
101 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
7 February 2024
Proposed online date
December 2027
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County