United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 9 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1145, Callaway County
Solar
250 MWAgreement signed Callaway, MOMISO Mar 2018target 2024
Goldfinch Solar
Solar · Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Solar project J3805, Fayette County
Solar
250 MWIn study Fayette, ILMISO Mar 2024target 2027
Solar project J2602, Desoto County
Solar
250 MWIn study Desoto, MSMISO Sep 2022target 2026
Solar project GEN-2021-047, Mayes County
Solar
250 MWAgreement signed Mayes, OKSPP Apr 2021target 2029
Solar project 25-IC-1326, Jasper County
Solar
250 MWIn study Jasper, GASoutheast Apr 2025target 2030
Solar project J1873, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Solar project AH2-069, Wythe County
Solar
250 MWIn study Wythe, VAPJM Jan 2022target 2025
Solar project J2921, Calhoun County
Solar
250 MWIn study Calhoun, MIMISO Sep 2022target 2026
Solar project S0006, Carbon County
Solar · PacifiCorp
250 MWIn study Carbon, WYWest Mar 2022target 2026
August Draw Solar
Solar · August Draw Solar Holdings, LLC
250 MWAgreement signed Reeves, TXERCOT Sep 2022target 2028
Solar project J2371, Morehouse Parish County
Solar
250 MWIn study Morehouse Parish, LAMISO Sep 2022target 2026
Solar project J4152, Redwood County
Solar
250 MWIn study Redwood, MNMISO Oct 2025target 2028
Solar project J2180, Sabine Parish County
Solar
250 MWIn study Sabine Parish, LAMISO Jul 2022target 2027
Samson Solar 1
Solar · Samson Solar Energy LLC
250 MWAgreement signed Lamar, TXERCOT Nov 2018target 2026
Solar project J2922, Jasper County
Solar
250 MWIn study Jasper, ILMISO Sep 2022target 2028
Solar project Q03, Kern County
Solar
250 MWUnder construction Kern, CAWest Sep 2007target 2014
Solar project J2523, Independence County
Solar
250 MWIn study Independence, ARMISO Sep 2022target 2026
Solar project GEN-2020-094, Otoe County
Solar
250 MWAgreement signed Otoe, NESPP Apr 2020target 2030
Solar project IC-1149, Mitchell County
Solar
250 MWPaused / redesign Mitchell, GASoutheast Jul 2023target 2028
Solar project J3954, Christian County
Solar
250 MWIn study Christian, ILMISO Apr 2025target 2030
Solar project J3556, Montgomery County
Solar
250 MWIn study Montgomery, ILMISO Apr 2024target 2028
Solar project BHBE G20, Dawes County
Solar
250 MWAgreement signed Dawes, SDWest Jul 2022target 2025
Solar project J1415, Lonoke County
Solar
250 MWAgreement signed Lonoke, ARMISO Apr 2019target 2024
Solar project GEN-2024-039, Nemaha County
Solar
250 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar project J1614, Muskegon County
Solar
250 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project GEN-2024-032, Stevens County
Solar
250 MWIn study Stevens, KSSPP Oct 2024target 2028
Solar project J1840, Dewitt County
Solar
250 MWIn study Dewitt, ILMISO Jun 2020target 2023
Solar project Company 170, Clark County
Solar
250 MWPaused / redesign Clark, NVWest Sep 2018target 2023
Solar project GEN-2024-139, Coffey County
Solar
250 MWIn study Coffey, KSSPP Mar 2025target 2033
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
Solar project J4080, Jefferson County
Solar
250 MWIn study Jefferson, ARMISO Oct 2025target 2030
Iguala Solar
Solar
250 MWPaused / redesign Victoria, TXERCOT Oct 2020target 2025
Solar project AG2-029, Noble County
Solar · Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project S0005, Carbon County
Solar · PacifiCorp
250 MWIn study Carbon, WYWest Mar 2022target 2026
Solar project J2662, Cumberland County
Solar
250 MWIn study Cumberland, ILMISO Sep 2022target 2026
Solar project AG2-163, Fountain County
Solar · Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Solar project J3882, Crawford County
Solar
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Solar project J2294, Mississippi County
Solar
250 MWIn study Mississippi, ARMISO Aug 2021target 2028
Solar project J3911, Louisa County
Solar
250 MWIn study Louisa, IAMISO Feb 2025target 2030
Solar project IC-696, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project IC-972, Jasper County
Solar
250 MWPaused / redesign Jasper, GASoutheast Jul 2021target 2024
Solar project 171, Williamsburg County
Solar
249 MWUnder construction Williamsburg, SCSoutheast Oct 2021target 2028
Solar project J3787, Stutsman County
Solar
247 MWIn study Stutsman, NDMISO Apr 2024target 2028
Solar project J4031, Scott County
Solar
245 MWIn study Scott, ILMISO May 2025target 2030
Solar project GI-120, Randolph County
Solar
245 MWAgreement signed Randolph, MOSoutheast Apr 2024target 2031
Solar project J3945, Washtenaw County
Solar
245 MWIn study Washtenaw, MIMISO Apr 2025target 2030
Morada Del Sol Solar
Solar · First Solar
245 MWPaused / redesign Upton, TXERCOT Mar 2015target 2020
Solar project J4147, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Page 9 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)