United States › Grid › Interconnection queues › Iowa
SOLAR · MISOSolar project J3911, Louisa County
Solar project J3911, Louisa County is a 250 MW solar request in interconnection study in the MISO interconnection queue, in Louisa County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3911
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- SUB 93 LOUISA - SUB T HASKINS 345.0kV
- Location
- Louisa County, Iowa
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 25 February 2025
- Proposed online date
- June 2030
Location
Marker shows the centre of Louisa County; the queue data does not give exact sites.
Other requests in Louisa County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem