🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Dakota

SOLAR · MISO

Solar project J3787, Stutsman County

Solar project J3787, Stutsman County is a 247 MW solar request in interconnection study in the MISO interconnection queue, in Stutsman County, North Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3787
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Jamestown 345 kV Substation
Location
Stutsman County, North Dakota
Technology
Solar: 247 MW
Total requested
247 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
June 2028

Location

Marker shows the centre of Stutsman County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Stutsman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem