Solar project J1145, Callaway County

Solar project J1145, Callaway County is a 250 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Callaway County, Missouri, connecting to Ameren Missouri.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMar 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1145
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Overton - (McCrede) - Montgomery 345 kV Line Tap
Location
Callaway County, Missouri
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
12 March 2018
Agreement signed
31 March 2022
Proposed online date
June 2024

Location

Marker shows the centre of Callaway County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Callaway County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem