United States › Grid › Interconnection queues › Missouri
NUCLEAR · MISONuclear project G475, Callaway County
Nuclear project G475, Callaway County is a 56.0 MW nuclear request built and operating in the MISO interconnection queue, in Callaway County, Missouri.
Request details
- Queue ID
- G475
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Callaway Nuclear Station
- Location
- Callaway County, Missouri
- Technology
- Nuclear: 56.0 MW
- Total requested
- 56.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 7 October 2004
- Agreement signed
- 3 February 2006
- Proposed online date
- November 2007
- Came online
- November 2007
Location
Marker shows the centre of Callaway County; the queue data does not give exact sites.
Other requests in Callaway County
- Solar project J1145, Callaway CountySolar · 250 MW · agreement signed
- Solar + storage project J2205, Callaway CountySolar + storage · 300 MW · in study
- Solar project J1836, Callaway CountySolar · 300 MW · in study
- Nuclear project G733, Callaway CountyNuclear · 1,650 MW · withdrawn
- Solar project J2043, Callaway CountySolar · 300 MW · withdrawn
- Solar project J3307, Callaway CountySolar · 300 MW · withdrawn
- Solar project GI-80, Callaway CountySolar · 250 MW · withdrawn
- Solar project J1965, Callaway CountySolar · 150 MW · withdrawn
- Solar project J2121, Callaway CountySolar · 100 MW · withdrawn
- Solar project J994, Callaway CountySolar · 100 MW · withdrawn
- Battery storage project J2008, Callaway CountyBattery storage · 65.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem