SOLAR · SPPSolar project GEN-2024-039, Nemaha County
Solar project GEN-2024-039, Nemaha County is a 250 MW solar request in interconnection study in the SPP interconnection queue, in Nemaha County, Nebraska, connecting to OPPD.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-039
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Humboldt - S1280 161 kV line
- Location
- Nemaha County, Nebraska
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 30 October 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Nemaha County; the queue data does not give exact sites.
Other requests in Nemaha County
- Solar project GEN-2024-038, Nemaha CountySolar · 300 MW · in study
- Solar project GEN-2024-040, Nemaha CountySolar · 174 MW · in study
- Solar project GEN-2019-009, Nemaha CountySolar · 100 MW · suspended
- Onshore wind project GEN-2018-110, Nemaha CountyOnshore wind · 500 MW · withdrawn
- Nuclear project GEN-2012-017, Nemaha CountyNuclear · 115 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem