Interconnection queue in Texas (2024 requests) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown452109.5 GW
Active in queue109.5 GW452 requests
Agreement signed17.3 GW74 requests
Withdrawn429,552 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

452 requests · page 9 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Brahman Renewables Solar
Solar + storage · Brahman Renewables
101 MWIn study Milam, TXERCOT Oct 2024target 2029
Musgravite Solar
Solar · BT Thompson Solar, LLC
101 MWIn study Henderson, TXERCOT Mar 2024target 2027
Sugarloaf BESS
Battery storage · Sugarloaf Clean Energy LLC
101 MWIn study Dimmit, TXERCOT Mar 2024target 2028
Cobra Clean Energy Center
Battery storage · Cobra Clean Energy Center LLC
100 MWIn study Brazoria, TXERCOT Feb 2024target 2027
Jim Wells BESS
Battery storage · Jim Wells ESS
100 MWIn study Jim Wells, TXERCOT Feb 2024target 2028
Ne100B
Battery storage
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Callisto ID Energy Center
Battery storage · Tempus Power management LLC
100 MWIn study Harris, TXERCOT Oct 2024target 2026
Ne100S
Solar
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Adam Bryant BESS
Battery storage · Adam Bryant BESS LLC
99.5 MWIn study Medina, TXERCOT Feb 2024target 2027
Cannibal Draw Storage
Solar + storage · Cannibal Draw Solar, LLC
98.6 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Anawa La Solar
Solar + storage · Anawa La Solar LLC
93.3 MWIn study Hidalgo, TXERCOT Mar 2024target 2027
Basketflower Storage
Solar + storage · Basketflower Solar, LLC
92.0 MWIn study Eastland, TXERCOT Oct 2024target 2027
Raghorn Solar SLF
Solar + storage · Raghorn Solar LLC
91.9 MWIn study Jim Wells, TXERCOT May 2024target 2027
Callan Solar
Solar · Menard PV, LLC
91.0 MWIn study Menard, TXERCOT Jun 2024target 2028
Wild Horse Desert Storage
Solar + storage · Wild Horse Desert Solar, LLC
90.3 MWIn study Dimmit, TXERCOT Dec 2024target 2028
Billie Storage
Battery storage · Weslaco Storage LLC
83.8 MWIn study Hidalgo, TXERCOT Jul 2024target 2029
M-Bar BESS I
Solar + storage · M-Bar Energy I, LLC
82.1 MWIn study Ector, TXERCOT Dec 2024target 2028
Juniperusss
Solar + storage · BLUE STONE RENEWABLE XXI LLC
80.3 MWIn study Hopkins, TXERCOT Jan 2024target 2029
Knox County Moore Storage
Battery storage · DM-KCM, LLC
77.0 MWIn study Knox, TXERCOT Dec 2024target 2028
Solar + storage project GEN-2024-071, Cass County
Solar + storage
75.0 MWIn study Cass, TXSPP Oct 2024target 2027
Sunbeam Solar
Solar · Buckeye Midway Solar
74.4 MWIn study San Patricio, TXERCOT Oct 2024target 2028
Sullivan BESS
Solar + storage · Sullivan Solar LLC
72.2 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Symank Solar
Solar · BT Symank Solar, LLC
66.6 MWIn study Bosque, TXERCOT Nov 2024target 2027
Little Star Solar
Solar · RWE Clean Energy Development, LLC
61.6 MWIn study Bastrop, TXERCOT Jul 2024target 2026
Beaverhead Solar SLF
Solar + storage · Beaverhead Solar, LLC
61.5 MWIn study Jim Wells, TXERCOT Aug 2024target 2027
Beaverhead Storage SLF
Solar + storage · Beaverhead Solar, LLC
61.5 MWIn study Jim Wells, TXERCOT Aug 2024target 2027
Centennial Solar
Solar · Centennial AD 8 LLC
61.4 MWIn study Menard, TXERCOT Jan 2024target 2029
Fallstone Solar SLF
Solar + storage · Fallstone Solar, LLC
60.6 MWIn study Falls, TXERCOT Dec 2024target 2028
Hondo Arroyo Solar
Solar + storage · Hondo Creek Solar, LLC
60.4 MWIn study Medina, TXERCOT Jun 2024target 2028
Tipperary Solar
Solar · Tippsol
60.2 MWIn study Schleicher, TXERCOT Jun 2024target 2028
Stonewall Solar
Solar + storage · Stonewall PV, LLC
60.2 MWIn study Stonewall, TXERCOT May 2024target 2029
Donna BESS
Solar + storage · Donna Solar LLC
53.9 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Paloma Energy Center BESS
Solar + storage · Harrison Street Development, LLC
53.6 MWIn study Colorado, TXERCOT Feb 2024target 2027
Fluvanna Max BESS SLF
Solar + storage · Fluvanna Max Solar LLC
51.8 MWIn study Scurry, TXERCOT Dec 2024target 2029
Findley BESS
Solar + storage · Gransolar Texas Sixteen, LLC
51.7 MWIn study Limestone, TXERCOT Feb 2024target 2028
Sword BESS
Solar + storage · Hidalgo Solar LLC
44.4 MWIn study Starr, TXERCOT Mar 2024target 2029
Electric E - West Texas Generation
Gas · Electric E Power Marketing
43.6 MWIn study Loving, TXERCOT Oct 2024target 2028
Graphic Packaging Gas
Gas · Graphic Packaging International
43.4 MWIn study Mclennan, TXERCOT Jan 2024target 2026
La Mancha Storage SLF
Solar + storage · La Mancha Storage, LLC
40.9 MWIn study Zavala, TXERCOT Nov 2024target 2028
La Mancha Solar SLF
Solar + storage · La Mancha Solar, LLC
40.9 MWIn study Zavala, TXERCOT Nov 2024target 2028
Buck Ranch Solar SLF
Solar + storage · Buck Ranch Solar, LLC
40.8 MWIn study Live Oak, TXERCOT Dec 2024target 2028
M-Bar Solar I
Solar + storage · M-Bar Energy I, LLC
30.2 MWIn study Ector, TXERCOT Dec 2024target 2028
Hillboro Wind
Wind + storage · Abei Energy Green XI LLC
27.8 MWIn study Hill, TXERCOT Jul 2024target 2028
Zeus Rusk Solar
Solar + storage · Rusk Solar, LLC
26.8 MWIn study Rusk, TXERCOT Mar 2024target 2027
Shannon Wind Repower
Onshore wind · Shannon Wind, LLC
18.5 MWIn study Archer, TXERCOT Feb 2024target 2027
Empire Central BESS
Battery storage · SMT Dallas III LLC
10.0 MWAgreement signed Dallas, TXERCOT Jan 2024target 2025
Carrizo Springs BESS
Battery storage · Regis Carrizo Springs LLC
10.0 MWAgreement signed Dimmit, TXERCOT Aug 20242025
Poteet BESS
Battery storage · HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Atascosa, TXERCOT Oct 2024target 2026
Lantana BESS
Battery storage · Aggreko MSR Grid PC2
10.0 MWAgreement signed Nueces, TXERCOT Apr 2024target 2026
Abilene Elmcreek BESS
Battery storage · DGSP2 LLC
9.9 MWAgreement signed Taylor, TXERCOT Sep 2024target 2026
Page 9 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)