United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTJim Wells BESS
Jim Wells BESS is a 100 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Jim Wells County, Texas.
Queue statusIn planning
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0154
- Grid region
- ERCOT (Texas)
- Developer
- Jim Wells ESS
- Connection point (POI)
- 69kV PREMONT (#8894)
- Location
- Jim Wells County, Texas
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 7 February 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Jim Wells County; the queue data does not give exact sites.
Other requests in Jim Wells County
- Orange Grove BESSSolar + storage · 61.4 MW · agreement signed
- BESS StadiumBattery storage · 9.9 MW · agreement signed
- Raghorn Solar SLFSolar + storage · 91.9 MW · in study
- Beaverhead Solar SLFSolar + storage · 61.5 MW · in study
- Beaverhead Storage SLFSolar + storage · 61.5 MW · in study
- Bandana Solar SLFSolar · 86.9 MW · suspended
- Orange Grove SolarSolar + storage · 131 MW · built
- Osprey1Gas · 150 MW · withdrawn
- Millhouse SolarSolar · 75.0 MW · withdrawn
- Millhouse StorageOther · 38.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem