United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA — page 86
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project G0857, Powell County Onshore wind |
300 MW | Withdrawn / abandoned |
| Zapata I W Onshore wind · Nextera |
300 MW | Withdrawn / abandoned |
| Solar + storage project G0929, Deschutes County Solar + storage |
300 MW | Withdrawn / abandoned |
| Gas project Q11, Middlesex County Gas |
300 MW | Withdrawn / abandoned |
| Beltran Solar Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project 711, Power County Solar + storage |
300 MW | Withdrawn / abandoned |
| Homer Mountain Wind Farm Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project AI1-205 Battery storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q514, Yuma County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-034, Utah County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project 116, Kittitas County Solar + storage |
300 MW | Withdrawn / abandoned |
| Birch Solar Solar |
300 MW | Withdrawn / abandoned |
| Solar project J1337, Sherburne County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project J3920, Clay County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2008-026, Thomas County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project G416, Washington County Gas |
300 MW | Withdrawn / abandoned |
| Onshore wind project H014, Rush County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GI-2017-30, Pueblo County Solar |
300 MW | Withdrawn / abandoned |
| Coopers Corner BESS Battery storage · ACE DevCo NC,LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-112, Craig County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project C3-053, Utah County Gas |
300 MW | Withdrawn / abandoned |
| Solar project 784, Power County Solar |
300 MW | Withdrawn / abandoned |
| Sterling Energy Center Onshore wind · Invenergy |
300 MW | Withdrawn / abandoned |
| Onshore wind project J713, Oliver County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project 934, Albany County Onshore wind |
300 MW | Withdrawn / abandoned |
| Tule II Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project 163, Apache County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project J3995, Jasper County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2023-200, Elk County Solar |
300 MW | Withdrawn / abandoned |
| Frederickson Power LP Gas · Frederickson Power, LP |
300 MW | Withdrawn / abandoned |
| Onshore wind project AG2-452, Auglaize County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project AG1-119, Dekalb County Solar · Leeward Renewable Energy Development, LLC |
300 MW | Withdrawn / abandoned |
| Athens Energy Storage Battery storage · Athens Energy Stoarge LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project 133, Garfield County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project AF1-034, Highland County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project 929, Platte County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project 1202, San Juan County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project GEN-2023-026, Anderson County Battery storage |
300 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
300 MW | Withdrawn / abandoned |
| Enron Power Marketing Gas · Enron Power Marketing, Inc. |
300 MW | Withdrawn / abandoned |
| Gas project J131, Lyon County Gas |
300 MW | Withdrawn / abandoned |
| Wind + storage project T2-036, Sweetwater County Wind + storage |
300 MW | Withdrawn / abandoned |
| Solar project AG1-525, Sullivan County Solar · PJM Solar Devco I, LLC |
300 MW | Withdrawn / abandoned |
| Bayonne Gas · Calpine Energy Services |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2023-176, Lamb County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project C2-68, Bannock County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2024-100, Castro County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2022-105, Tillman County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project C4-106, Bingham County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2023-100, Woods County Solar + storage |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)