πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

BATTERY STORAGE Β· PJM

Battery storage project AI1-205

Battery storage project AI1-205 is a 300 MW battery storage request withdrawn in the PJM interconnection queue, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedNov 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AI1-205
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Brokaw 345 kV
Location
Illinois
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2022
Proposed online date
December 2028
Withdrawn
November 2022

Location

No county location in the queue data.

Power plants in Illinois Β· Transmission lines in Illinois

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem