Enron Power Marketing

Enron Power Marketing is a 300 MW gas request withdrawn in the West interconnection queue, in King County, Washington, connecting to Enron Power Marketing, Inc..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G89
Grid region
West (non-ISO utilities)
Utility / transmission owner
Enron Power Marketing, Inc.
Developer
Enron Power Marketing, Inc.
Connection point (POI)
Maple Valley 230 kV Substation
Location
King County, Washington
Technology
Gas: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
23 November 2001
Proposed online date
January 2004

Location

Marker shows the centre of King County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in King County