BATTERY STORAGE Β· SPPBattery storage project GEN-2023-026, Anderson County
Battery storage project GEN-2023-026, Anderson County is a 300 MW battery storage request withdrawn in the SPP interconnection queue, in Anderson County, Kansas, connecting to Evergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-026
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Evergy
- Connection point (POI)
- LaCygne - Wolf Creek 345 kV Line
- Location
- Anderson County, Kansas
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- June 2027
- Withdrawn
- March 2024
Location
Marker shows the centre of Anderson County; the queue data does not give exact sites.
Other requests in Anderson County
- Onshore wind project GEN-2004-011, Anderson CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project GEN-2007-022, Anderson CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project GEN-2005-001, Anderson CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project GEN-2005-014, Anderson CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project GEN-2016-012, Anderson CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2010-050, Anderson CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem