Queue requests in study in the USA — page 84

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 84 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 2024-G2, Shasta County
Solar + storage
125 MWIn study Shasta, CAWest Nov 2024target 2028
Bluestem Solar
Solar · RWE Solar Development, LLC
125 MWIn study Laporte, INPJM Sep 2020target 2023
Solar project J2490, Tuscola County
Solar
125 MWIn study Tuscola, MIMISO Sep 2022target 2025
East Setauket Energy Storage
Battery storage · East Setauket Energy Storage, LLC
125 MWIn study Suffolk, NYNYISO Jan 2020target 2027
Solar + storage project J2826, Greene County
Solar + storage
125 MWIn study Greene, INMISO Sep 2022target 2027
Solar + storage project GEN-2023-092, Choctaw County
Solar + storage
125 MWIn study Choctaw, OKSPP Oct 2023target 2028
Solar project C2-167, Emery County
Solar · PacifiCorp
125 MWIn study Emery, UTWest May 2022target 2026
Battery storage project 21-11157, Larimer County
Battery storage
125 MWIn study Larimer, COWest Nov 2021target 2026
Other project GEN-2025-SR15, Mcclain County
Other
125 MWIn study Mcclain, OKSPP May 2025target 2029
TOCE GA 1 Solar
Solar
125 MWIn study Burke, GASoutheast Aug 2023target 2026
Solar project J2881, Jefferson County
Solar
125 MWIn study Jefferson, ARMISO Sep 2022target 2026
Battery storage project Q423, Navajo County
Battery storage
125 MWIn study Navajo, AZWest Sep 2021target 2025
Solar project J1620, Pipestone County
Solar
125 MWIn study Pipestone, MNMISO Apr 2024target 2026
Battery storage project 121, King County
Battery storage
125 MWPaused / redesign King, WAWest Aug 2021target 2030
Solar project J1679, Clay County
Solar
125 MWIn study Clay, ILMISO Jun 2020target 2026
Battery storage project Q384, Maricopa County
Battery storage
125 MWPaused / redesign Maricopa, AZWest Mar 2021target 2025
Solar project J2751, Bolivar County
Solar
125 MWIn study Bolivar, MSMISO Sep 2022target 2026
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Solar project J2384, Shelby County
Solar
125 MWIn study Shelby, ILMISO Sep 2022target 2024
Solar project J3792, Gratiot County
Solar
125 MWIn study Gratiot, MIMISO Apr 2024target 2028
Journey Solar
Solar · Journey Solar, LLC
125 MWIn study Haskell, TXERCOT Mar 2024target 2027
Battery storage project GEN-2023-SR22, Mayes County
Battery storage
125 MWIn study Mayes, OKSPP Jun 20232024
Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar
Other
124 MWIn study MISO Feb 20222024
El Rey Power Bank
Battery storage
124 MWIn study Monterey, CACAISO Apr 2021target 2029
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Solar project J2187, Laporte County
Solar
124 MWIn study Laporte, INMISO Mar 2022target 2024
EMPower Odessa (TEF - Due Diligence)
Gas · EMPOWER USA, LLC
123 MWIn study Ector, TXERCOT Jul 2024target 2028
Bonita Bateria 2
Battery storage
123 MWIn study Orange, CACAISO Apr 2023target 2029
Sleepy Hollow BESS
Battery storage · Sleepy Hollow BESS, LLC
123 MWIn study Throckmorton, TXERCOT Nov 2023target 2028
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Great Hambino BESS
Battery storage · Atascosa BESS, LLC
123 MWIn study Atascosa, TXERCOT Sep 2025target 2027
Signal Hill BESS I
Battery storage · Signal Hill Generating LLC
123 MWIn study Wichita, TXERCOT Sep 2024target 2027
Prairie Blossom Storage
Battery storage · Prairie Blossom Storage, LLC
123 MWIn study Howard, TXERCOT Dec 2024target 2028
Arnold Hills Storage
Battery storage · Arnold Hills Storage, LLC
123 MWIn study Henderson, TXERCOT Mar 2025target 2029
Dove Wing Storage
Battery storage · Dove Run Solar Project, LLC
122 MWIn study Duval, TXERCOT Feb 2024target 2028
Sayle Solar SLF
Solar + storage · Sayle Solar LLC
122 MWIn study Jackson, TXERCOT Jun 2024target 2027
Morning Glory Solar
Solar · Armadillo Solar, LLC
122 MWIn study Tom Green, TXERCOT Jun 2021target 2026
Sayle Storage SLF
Solar + storage · Sayle Storage LLC
122 MWIn study Jackson, TXERCOT Jun 2024target 2027
Solar project 790, Washington County
Solar
122 MWIn study Washington, IDWest Apr 2025target 2030
Battery storage project S0033, Washington County
Battery storage
122 MWIn study Washington, UTWest Dec 2024target 2027
BRP Ampato BESS
Battery storage · BRP Ampato BESS LLC
122 MWIn study Crane, TXERCOT Aug 2020target 2027
Wildhorse Energy Center
Battery storage
122 MWIn study Sonoma, CACAISO Apr 2021target 2030
Bronc Rodeo Solar Project
Solar · Energiekontor US Texas SP 16 LLC
122 MWIn study Falls, TXERCOT May 2023target 2028
Nymphaea Solar
Solar + storage · Nymphaea Solar, LLC
121 MWIn study Wichita, TXERCOT Sep 2022target 2028
Marengo BESS
Battery storage · BRP BLUE TOPAZ 8, LLC
121 MWIn study Cameron, TXERCOT May 2023target 2028
Iron Cowboy Solar
Solar + storage · Vaquero II Solar, LLC
121 MWIn study San Patricio, TXERCOT Jun 2025target 2028
High Winds Storage
Battery storage
121 MWIn study Solano, CACAISO Apr 2021target 2031
Wagyu BESS SLF
Battery storage · Wagyu BESS, LLC
121 MWIn study Brazoria, TXERCOT Jun 2025target 2026
Borden Dino Solar
Solar + storage · Borden Dino Solar, LLC
121 MWIn study Borden, TXERCOT Apr 2025target 2028
Neal Battery
Solar + storage · CH Neal Battery LLC
121 MWIn study Wharton, TXERCOT Oct 2025target 2029
Page 84 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)