Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 8 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J1485, Deuel County
Onshore wind
250 MWIn study Deuel, SDMISO Apr 2019target 2022
Solar project J3805, Fayette County
Solar
250 MWIn study Fayette, ILMISO Mar 2024target 2027
Battery storage project J3656, Saginaw County
Battery storage
250 MWIn study Saginaw, MIMISO Mar 2024target 2028
Solar project J2602, Desoto County
Solar
250 MWIn study Desoto, MSMISO Sep 2022target 2026
Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2
Solar + storage
250 MWIn study Pike, INMISO Oct 2021target 2024
Solar project J1873, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Battery storage project J3848, Wabasha County
Battery storage
250 MWIn study Wabasha, MNMISO Dec 2024target 2030
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Solar project J2921, Calhoun County
Solar
250 MWIn study Calhoun, MIMISO Sep 2022target 2026
Battery storage project J3977, Sanilac County
Battery storage
250 MWIn study Sanilac, MIMISO Mar 2025target 2029
Solar project J2371, Morehouse Parish County
Solar
250 MWIn study Morehouse Parish, LAMISO Sep 2022target 2026
Solar project J4152, Redwood County
Solar
250 MWIn study Redwood, MNMISO Oct 2025target 2028
Onshore wind project J3639, Columbia County
Onshore wind
250 MWIn study Columbia, WIMISO Apr 2024target 2028
Solar project J2180, Sabine Parish County
Solar
250 MWIn study Sabine Parish, LAMISO Jul 2022target 2027
Solar project J2922, Jasper County
Solar
250 MWIn study Jasper, ILMISO Sep 2022target 2028
Battery storage project J2581, Ripley County
Battery storage
250 MWIn study Ripley, INMISO Sep 2022target 2026
Onshore wind project J3865, Shiawassee County
Onshore wind
250 MWIn study Shiawassee, MIMISO Dec 2024target 2028
Solar project J2523, Independence County
Solar
250 MWIn study Independence, ARMISO Sep 2022target 2026
Onshore wind project J3750, Mercer County
Onshore wind
250 MWIn study Mercer, ILMISO Apr 2024target 2028
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Solar project J3954, Christian County
Solar
250 MWIn study Christian, ILMISO Apr 2025target 2030
Solar project J3556, Montgomery County
Solar
250 MWIn study Montgomery, ILMISO Apr 2024target 2028
Onshore wind project J3929, Audrain County
Onshore wind
250 MWIn study Audrain, MOMISO Jan 2025target 2030
Solar project J1415, Lonoke County
Solar
250 MWAgreement signed Lonoke, ARMISO Apr 2019target 2024
Solar + storage project J2272, Clinton County
Solar + storage
250 MWIn study Clinton, IAMISO Jul 2021target 2026
Onshore wind project J1040, Mcintosh County
Onshore wind
250 MWUnder construction Mcintosh, NDMISO Mar 2018target 2023
Battery storage project J4081, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Onshore wind project J4018, Ford County
Onshore wind
250 MWIn study Ford, ILMISO May 2025target 2029
Solar project J1614, Muskegon County
Solar
250 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project J1840, Dewitt County
Solar
250 MWIn study Dewitt, ILMISO Jun 2020target 2023
Solar + storage project J4201, Beauregard Parish County
Solar + storage
250 MWIn study Beauregard Parish, LAMISO Sep 2025target 2029
Battery storage project J3894, Lyon County
Battery storage
250 MWIn study Lyon, MNMISO Feb 2025target 2030
Battery storage project J4118, Mclean County
Battery storage
250 MWIn study Mclean, ILMISO Sep 2025target 2030
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
Solar project J4080, Jefferson County
Solar
250 MWIn study Jefferson, ARMISO Oct 2025target 2030
Battery storage project J3438, Saginaw County
Battery storage
250 MWIn study Saginaw, MIMISO Mar 2024target 2028
Wind + storage project J3443, Big Stone County
Wind + storage
250 MWIn study Big Stone, MNMISO Apr 2024target 2028
Battery storage project J2091, Desoto County
Battery storage
250 MWIn study Desoto, MSMISO Jan 2022target 2025
Solar + storage project J2899, Calcasieu Parish County
Solar + storage
250 MWIn study Calcasieu Parish, LAMISO Sep 2022target 2026
Solar project J2662, Cumberland County
Solar
250 MWIn study Cumberland, ILMISO Sep 2022target 2026
Solar project J3882, Crawford County
Solar
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Solar project J2294, Mississippi County
Solar
250 MWIn study Mississippi, ARMISO Aug 2021target 2028
Solar project J3911, Louisa County
Solar
250 MWIn study Louisa, IAMISO Feb 2025target 2030
Battery storage project J3235, Benton County
Battery storage
250 MWIn study Benton, MNMISO Mar 2024target 2028
Onshore wind project J3275, Benton County
Onshore wind
249 MWIn study Benton, MNMISO Apr 2024target 2028
FERMI Storage Project
Battery storage · DTE Electric
248 MWIn study Monroe, MIMISO Aug 2025target 2028
Solar project J3787, Stutsman County
Solar
247 MWIn study Stutsman, NDMISO Apr 2024target 2028
Onshore wind project J476, Atchison County
Onshore wind
246 MWAgreement signed Atchison, MOMISO Sep 2015target 2021
Solar project J4031, Scott County
Solar
245 MWIn study Scott, ILMISO May 2025target 2030
Page 8 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)