United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA (2021 requests) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown616153.0 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

616 requests · page 7 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C1-16, Millard County
Solar + storage · Neptune Solar Energy Park LLC
199 MWPaused / redesign Millard, UTWest May 2021target 2025
Solar project J2047, Desoto County
Solar
199 MWIn study Desoto, MSMISO Aug 2021target 2024
Solar + storage project GI-2021-6, Adams County
Solar + storage
199 MWPaused / redesign Adams, COWest Apr 2021target 2024
Solar + storage project C1-54, Utah County
Solar + storage · Pinyon Creek Solar LLC
199 MWPaused / redesign Utah, UTWest May 2021target 2024
Solar + storage project C1-46, Klamath County
Solar + storage · Diamond Solar Energy LLC
199 MWIn study Klamath, ORWest May 2021target 2029
Percy Farm Solar
Solar · Percy Farm Solar 1, LLC
199 MWIn study Matagorda, TXERCOT Mar 2021target 2029
Solar project J2071, Hardin County
Solar
198 MWIn study Hardin, TXMISO Sep 2021target 2028
Buttercup Hybrid Solar
Solar + storage
197 MWIn study Merced, CACAISO Apr 2021target 2032
Solar project J1944, Sanilac County
Solar
185 MWIn study Sanilac, MIMISO Aug 2021target 2023
Solar project J2237, Lee County
Solar
185 MWIn study Lee, ARMISO Dec 2021target 2027
Solar project J1851, Morehouse Parish County
Solar
185 MWIn study Morehouse Parish, LAMISO Nov 2021target 2026
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Hofbrau BESS
Battery storage · Momentum Hofbrau LLC
181 MWIn study Tom Green, TXERCOT Sep 2021target 2028
Solar + storage project J2219, Olmsted County
Solar + storage
180 MWIn study Olmsted, MNMISO Jul 2021target 2028
Solar + storage project GI-2021-149, Imperial County
Solar + storage
175 MWIn study Imperial, CAWest Nov 2021target 2024
Solar + storage project J2127, Jefferson Davis County
Solar + storage
173 MWIn study Jefferson Davis, MSMISO Aug 2021target 2027
Cascade Solar
Solar
171 MWPaused / redesign Brazoria, TXERCOT Feb 2021target 2024
Solar project J1917, Livingston County
Solar
165 MWIn study Livingston, MIMISO Aug 2021target 2023
Aster Solar
Solar · Aster Solar
161 MWIn study Guadalupe, TXERCOT Sep 2021target 2029
Solar + storage project 416, Broadwater County
Solar + storage
160 MWPaused / redesign Broadwater, MTWest Sep 2021target 2023
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Quarter Ranch Solar
Solar · Gransolar Texas Three LLC
154 MWIn study Zapata, TXERCOT Jul 2021target 2028
Thunder Road Energy Storage
Battery storage · Hecate Grid Thunder Road Storage LLC
153 MWIn study Dallas, TXERCOT Oct 2021target 2027
Eighteenmile Solar SLF
Solar + storage · Weser Solar, LLC
153 MWIn study Goliad, TXERCOT Aug 2021target 2026
Pradera Storage
Solar + storage · Pradera Storage, LLC
153 MWIn study Webb, TXERCOT Jan 2021target 2027
Stockdale Solar
Solar
153 MWPaused / redesign Wilson, TXERCOT Mar 2021target 2025
Bobor Storage
Battery storage
152 MWIn study Tulare, CACAISO Apr 2021target 2030
Heartfield Storage
Other · Belltown Power Texas
152 MWPaused / redesign Hidalgo, TXERCOT Sep 2021target 2023
Rock N' Roll Solar SLF
Solar + storage · Rock N‚Äô Roll Solar, LLC
152 MWIn study Brazoria, TXERCOT May 2021target 2027
Flores Storage
Battery storage
152 MWIn study Madera, CACAISO Apr 2021target 2031
Onshore wind project J2053, Redwood County
Onshore wind
152 MWIn study Redwood, MNMISO Aug 2021target 2025
Solar + storage project G0716, Benton County
Solar + storage
150 MWIn study Benton, WAWest Dec 2021target 2025
Solar project IC-989, Johnson County
Solar
150 MWPaused / redesign Johnson, GASoutheast Oct 2021target 2025
Photo BESS 2
Solar + storage · CED Development Inc.
150 MWIn study Uvalde, TXERCOT Oct 2021target 2027
Talbot Solar
Solar
150 MWIn study Talbot, GASoutheast Dec 20212023
Solar + storage project J2129, Barry County
Solar + storage
150 MWIn study Barry, MIMISO Aug 2021target 2024
Crossroads Solar
Solar + storage
150 MWIn study Liberty, GASoutheast Jun 2021target 2024
Solar + storage project C1-40, Yakima County
Solar + storage · CG Yakima County Solar I LLC
150 MWIn study Yakima, WAWest May 2021target 2025
Solar + storage project AH2-021, Barren County
Solar + storage
150 MWIn study Barren, KYPJM Oct 2021target 2026
Solar + storage project J2142, Adair County
Solar + storage
150 MWIn study Adair, MOMISO Nov 2021target 2024
Solar + storage project IC-964, Emanuel County
Solar + storage
150 MWPaused / redesign Emanuel, GASoutheast Jun 2021target 2025
Dellwood Solar
Solar + storage
150 MWIn study Emanuel, GASoutheast May 20212023
Solar + storage project 21-11121, Weld County
Solar + storage
150 MWIn study Weld, COWest Nov 2021target 2025
Triple B Solar Alt#2
Solar · Triple B Solar LLC
150 MWIn study Lampasas, TXERCOT Jun 2021target 2027
Huning Energy
Solar
150 MWIn study Valencia, NMWest Jul 2021target 2025
WA_150SB Project
Solar + storage
150 MWPaused / redesign Bernalillo, NMWest Sep 2021target 2026
Peregrine BESS
Solar + storage · CED Development Inc.
150 MWIn study Goliad, TXERCOT Feb 2021target 2027
Cherry Tree Solar
Solar + storage
150 MWIn study Washington, GASoutheast Dec 2021target 2025
Solar project J1856, Jackson County
Solar
150 MWIn study Jackson, ARMISO Nov 2021target 2026
Solar project J2131, Jasper County
Solar
150 MWIn study Jasper, ILMISO Aug 2021target 2027
Page 7 of 13

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)