Peregrine BESS

Peregrine BESS is a 150 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Goliad County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0206
Grid region
ERCOT (Texas)
Developer
CED Development Inc.
Connection point (POI)
tap 345kV 8624 Grissom - 8164 Coleto Creek
Location
Goliad County, Texas
Technology
Battery: 150 MW · Battery
Total requested
150 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
10 February 2021
Proposed online date
July 2027

Location

Marker shows the centre of Goliad County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Goliad County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem