BATTERY STORAGE · ERCOT

Coleto Creek ESS Addition

Coleto Creek ESS Addition is a 100 MW battery storage request suspended in the ERCOT interconnection queue, in Goliad County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Dec 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
22INR0275
Grid region
ERCOT (Texas)
Location
Goliad County, Texas
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Suspended
Entered queue
10 December 2019

Location

Marker shows the centre of Goliad County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Goliad County