🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Kuy Creek Storage 1 SLF

Kuy Creek Storage 1 SLF is a 152 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Goliad County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0304
Grid region
ERCOT (Texas)
Developer
Kuy Creek Storage 1 LLC
Connection point (POI)
Tap - Coleto Creek (Bus # 8162) - Victoria (Bus# 8172) 138 kV CKT 1
Location
Goliad County, Texas
Technology
Battery: 152 MW · Battery
Total requested
152 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
24 March 2025
Proposed online date
March 2029

Location

Marker shows the centre of Goliad County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Goliad County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem