🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Missouri

SOLAR + STORAGE · MISO

Solar + storage project J2142, Adair County

Solar + storage project J2142, Adair County is a 150 MW solar + storage request in interconnection study in the MISO interconnection queue, in Adair County, Missouri, connecting to AMEREN MISSOURI.

Queue statusIn planning
  1. PlanningQueued Nov 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2142
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Maywood - Zachary 345 kV line
Location
Adair County, Missouri
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
3 November 2021
Proposed online date
August 2024

Location

Marker shows the centre of Adair County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Adair County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem