Solar project J1182, Adair County

Solar project J1182, Adair County is a 250 MW solar request built and operating in the MISO interconnection queue, in Adair County, Missouri, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMar 2022 (completed)
  3. Construction (completed)
  4. OperatingNov 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1182
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Connection point (POI)
Zachary Substation 345 kV Bus
Location
Adair County, Missouri
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
18 March 2022
Proposed online date
November 2024
Came online
November 2024

Location

Marker shows the centre of Adair County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Adair County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem