United States › Grid › Interconnection queues › Missouri
SOLAR · MISOSolar project J1182, Adair County
Solar project J1182, Adair County is a 250 MW solar request built and operating in the MISO interconnection queue, in Adair County, Missouri, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.
Request details
- Queue ID
- J1182
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN TRANSMISSION COMPANY OF ILLINOIS
- Connection point (POI)
- Zachary Substation 345 kV Bus
- Location
- Adair County, Missouri
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 18 March 2022
- Proposed online date
- November 2024
- Came online
- November 2024
Location
Marker shows the centre of Adair County; the queue data does not give exact sites.
Other requests in Adair County
- Solar + storage project J3199, Adair CountySolar + storage · 300 MW · in study
- Solar + storage project J2142, Adair CountySolar + storage · 150 MW · in study
- Onshore wind project J598, Adair CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G578, Adair CountyOnshore wind · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem