ONSHORE WIND Β· MISOOnshore wind project G578, Adair County
Onshore wind project G578, Adair County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Adair County, Missouri.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2005 (completed)
- Withdrawn / abandonedSep 2008 (project stopped here)
- ConsentedSep 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G578
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Adair 161kV Substation
- Location
- Adair County, Missouri
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 20 December 2005
- Agreement signed
- 30 September 2008
- Proposed online date
- October 2006
- Withdrawn
- September 2008
Location
Marker shows the centre of Adair County; the queue data does not give exact sites.
Other requests in Adair County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem