United States › Grid › Interconnection queues › Missouri
SOLAR + STORAGE · MISOSolar + storage project J3199, Adair County
Solar + storage project J3199, Adair County is a 300 MW solar + storage request in interconnection study in the MISO interconnection queue, in Adair County, Missouri, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3199
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN TRANSMISSION COMPANY OF ILLINOIS
- Connection point (POI)
- Zachary 345kV
- Location
- Adair County, Missouri
- Technology
- Solar: 300 MW · Battery
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Adair County; the queue data does not give exact sites.
Other requests in Adair County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem