ONSHORE WIND Β· MISOOnshore wind project J598, Adair County
Onshore wind project J598, Adair County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Adair County, Missouri.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJan 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J598
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Zachary to Ottumwa 345kV tap
- Location
- Adair County, Missouri
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Study phase
- GIA
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- October 2021
- Withdrawn
- January 2020
Location
Marker shows the centre of Adair County; the queue data does not give exact sites.
Other requests in Adair County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem