πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Stockdale Solar

Stockdale Solar is a 153 MW solar request suspended in the ERCOT interconnection queue, in Wilson County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0193
Grid region
ERCOT (Texas)
Location
Wilson County, Texas
Technology
Solar: 153 MW
Total requested
153 MW
Queue status
Suspended
Entered queue
31 March 2021
Proposed online date
December 2025

Location

Marker shows the centre of Wilson County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Wilson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem