United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTLyssy BESS
Lyssy BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Wilson County, Texas.
Queue statusConsented
- Planning (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0597
- Grid region
- ERCOT (Texas)
- Developer
- Regis Lyssy LLC
- Connection point (POI)
- TSP Station Name: LYSSY TSP Station Code: LYSSY Load Name/ Load Transformer Name: Lyssy1 Bus # - PTI Bus Number: #8193 Voltage in kV (Transmission Level): 138 kV Node (associated w/ load/load XFMR in
- Location
- Wilson County, Texas
- Technology
- Battery: 9.9 MW
- Total requested
- 9.9 MW
- Study phase
- IA Executed
- Queue status
- Active
- Agreement signed
- 7 November 2023
- Proposed online date
- January 2026
Location
Marker shows the centre of Wilson County; the queue data does not give exact sites.
Other requests in Wilson County
- Cachena Solar SLFSolar + storage · 601 MW · agreement signed
- Anila BESSSolar + storage · 209 MW · agreement signed
- Anila SolarSolar + storage · 201 MW · agreement signed
- Moonstone Solar ProjectSolar · 146 MW · agreement signed
- Huisache SolarSolar + storage · 126 MW · agreement signed
- Huisache BESSSolar + storage · 101 MW · agreement signed
- Mojo SolarSolar + storage · 528 MW · in study
- Wilson BESSBattery storage · 410 MW · in study
- Mojo BESSSolar + storage · 246 MW · in study
- Marcelina StorageBattery storage · 203 MW · in study
- Strawberry Acres StorageBattery storage · 157 MW · in study
- Pandora SolarSolar · 252 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem