Strawberry Acres Storage

Strawberry Acres Storage is a 157 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Wilson County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0248
Grid region
ERCOT (Texas)
Developer
Strawberry Acres Energy Center, LLC
Connection point (POI)
5132 Eagle Creek Substation 138kV
Location
Wilson County, Texas
Technology
Battery: 157 MW
Total requested
157 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
23 November 2022
Proposed online date
September 2028

Location

Marker shows the centre of Wilson County; the queue data does not give exact sites.