United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTAster Solar
Aster Solar is a 161 MW solar request in interconnection study in the ERCOT interconnection queue, in Guadalupe County, Texas.
Queue statusIn planning
- PlanningQueued Sep 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0115
- Grid region
- ERCOT (Texas)
- Developer
- Aster Solar
- Connection point (POI)
- 7042 Zorn 345kV
- Location
- Guadalupe County, Texas
- Technology
- Solar: 161 MW
- Total requested
- 161 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 21 September 2021
- Proposed online date
- June 2029
Location
Marker shows the centre of Guadalupe County; the queue data does not give exact sites.
Other requests in Guadalupe County
- Rockridge SolarSolar · 211 MW · agreement signed
- Nockenut Springs Solar 2Solar · 203 MW · agreement signed
- Nockenut Springs Solar 1Solar · 203 MW · agreement signed
- Rio Nogales CT1 Rotor ReplacementGas · 3.1 MW · agreement signed
- CPS Rio Nogales CT301 Rotor ReplacementGas · 3.1 MW · agreement signed
- CPS Rio Nogales CT201 Rotor ReplacementGas · 3.1 MW · agreement signed
- Calpine Guadalupe PeakersGas · 450 MW · in study
- Guadalupe Battery Storage ProjectBattery storage · 211 MW · in study
- Ruedrich BESSBattery storage · 201 MW · in study
- Roble BESSBattery storage · 154 MW · in study
- Utica SolarSolar · 205 MW · suspended
- Utica BESSBattery storage · 204 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem