🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Rock N' Roll Solar SLF

Rock N' Roll Solar SLF is a 152 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0041
Grid region
ERCOT (Texas)
Developer
Rock N’ Roll Solar, LLC
Connection point (POI)
tap 138kV 44600 Rosharon - 44531 Winmil
Location
Brazoria County, Texas
Technology
Solar: 152 MW · Battery
Total requested
152 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
10 May 2021
Proposed online date
August 2027

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem