🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in SPP (Southwest Power Pool) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown480114.8 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

480 requests · page 7 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2024-055, Vernon County
Solar
175 MWIn study Vernon, MOSPP Oct 2024target 2029
Solar project ERAS-2025-025, Caddo County
Solar
175 MWIn study Caddo, OKSPP Oct 2025target 2027
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Battery storage project GEN-2024-034, Sargent County
Battery storage
175 MWIn study Sargent, NDSPP Oct 2024target 2029
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-084, Lawrence County
Battery storage
167 MWIn study Lawrence, MOSPP Oct 2024target 2028
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-085, Rush County
Solar
160 MWIn study Rush, KSSPP Oct 2024target 2029
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-122, Marion County
Solar + storage
160 MWIn study Marion, TXSPP Mar 2025target 2029
Solar project GEN-2024-072, Mitchell County
Solar
160 MWIn study Mitchell, KSSPP Oct 2024target 2029
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Solar + storage project GEN-2024-265, Lea County
Solar + storage
155 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-205, Stafford County
Solar + storage
155 MWIn study Stafford, KSSPP Mar 2025target 2029
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Solar + storage project GEN-2024-261, Lea County
Solar + storage
150 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-065, Dodge County
Battery storage
150 MWIn study Dodge, NESPP Oct 2024target 2029
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Battery storage project GEN-2023-170, Chariton County
Battery storage
150 MWIn study Chariton, MOSPP Oct 2023target 2028
Battery storage project GEN-2024-276, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Solar project GEN-2024-210, Cheyenne County
Solar
150 MWIn study Cheyenne, KSSPP Mar 2025target 2028
Battery storage project GEN-2023-171, Jackson County
Battery storage
150 MWIn study Jackson, MOSPP Oct 2023target 2028
Battery storage project GEN-2024-306, Lea County
Battery storage
150 MWIn study Lea, NMSPP Mar 2025target 2031
Solar + storage project ERAS-2025-032, Stafford County
Solar + storage
150 MWIn study Stafford, KSSPP Oct 2025target 2029
Battery storage project GEN-2022-238, Pottawatomie County
Battery storage
150 MWIn study Pottawatomie, OKSPP Feb 2023target 2028
Solar + storage project ERAS-2025-033, Ford County
Solar + storage
150 MWIn study Ford, KSSPP Oct 2025target 2027
Solar + storage project GEN-2023-230, Bossier Parish County
Solar + storage
150 MWIn study Bossier Parish, LASPP Oct 2023target 2028
Solar + storage project ERAS-2025-005, Yell County
Solar + storage
150 MWIn study Yell, ARSPP Sep 2025target 2029
Battery storage project GEN-2024-029, Logan County
Battery storage
150 MWIn study Logan, OKSPP Oct 2024target 2028
Battery storage project GEN-2022-017, Woodward County
Battery storage
150 MWIn study Woodward, OKSPP Jun 2022target 2028
Solar project GEN-2024-030, Gray County
Solar
150 MWIn study Gray, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-SR9, Beaver County
Battery storage
150 MWIn study Beaver, OKSPP Jan 2024target 2027
Solar project GEN-2023-132, Craighead County
Solar
150 MWIn study Craighead, ARSPP Oct 2023target 2028
Onshore wind project GEN-2021-021, Stevens County
Onshore wind
150 MWIn study Stevens, KSSPP Apr 2021target 2027
Battery storage project GEN-2024-332, Oklahoma County
Battery storage
150 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Solar project GEN-2024-283, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Battery storage project GEN-2025-SR4, Edwards County
Battery storage
150 MWIn study Edwards, KSSPP Aug 2025target 2028
Solar project GEN-2024-282, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Page 7 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)