United States › Grid › Interconnection queues › Kansas
SOLAR + STORAGE · SPPSolar + storage project ERAS-2025-033, Ford County
Solar + storage project ERAS-2025-033, Ford County is a 150 MW solar + storage request in interconnection study in the SPP interconnection queue, in Ford County, Kansas, connecting to SEPC.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- ERAS-2025-033
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SEPC
- Connection point (POI)
- Fort Dodge 115 kV Substation
- Location
- Ford County, Kansas
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- ERAS
- Queue status
- Active
- Entered queue
- 1 October 2025
- Proposed online date
- May 2027
Location
Marker shows the centre of Ford County; the queue data does not give exact sites.
Other requests in Ford County
- Onshore wind project GEN-2019-030, Ford CountyOnshore wind · 252 MW · agreement signed
- Solar project GEN-2023-SR28, Ford CountySolar · 150 MW · agreement signed
- Solar project GEN-2019-058, Ford CountySolar · 150 MW · agreement signed
- Solar project GEN-2019-044, Ford CountySolar · 100 MW · agreement signed
- Battery storage project GEN-2019-063, Ford CountyBattery storage · 50.0 MW · agreement signed
- Onshore wind project GEN-2024-193, Ford CountyOnshore wind · 250 MW · in study
- Onshore wind project GEN-2024-194, Ford CountyOnshore wind · 250 MW · in study
- Battery storage project GEN-2024-189, Ford CountyBattery storage · 199 MW · in study
- Onshore wind project GEN-2016-046, Ford CountyOnshore wind · 299 MW · built
- Onshore wind project GEN-2005-012, Ford CountyOnshore wind · 248 MW · built
- Onshore wind project GEN-2008-124, Ford CountyOnshore wind · 200 MW · built
- Onshore wind project GEN-2012-024, Ford CountyOnshore wind · 180 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem