🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2024-030, Gray County

Solar project GEN-2024-030, Gray County is a 150 MW solar request in interconnection study in the SPP interconnection queue, in Gray County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-030
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Santa Fe 115 kV Substation
Location
Gray County, Kansas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 October 2024
Proposed online date
December 2028

Location

Marker shows the centre of Gray County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Gray County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem