United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2008-079, Gray County

Onshore wind project GEN-2008-079, Gray County is a 98.9 MW onshore wind request built and operating in the SPP interconnection queue, in Gray County, Kansas, connecting to MKEC.

Queue statusOperating
  1. PlanningQueued Jul 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2008-079
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
MKEC
Connection point (POI)
Crooked Creek 115kV
Location
Gray County, Kansas
Technology
Wind: 98.9 MW
Total requested
98.9 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
29 July 2008
Proposed online date
November 2011
Came online
November 2011

Location

Marker shows the centre of Gray County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Gray County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem