Solar project GEN-2023-132, Craighead County

Solar project GEN-2023-132, Craighead County is a 150 MW solar request in interconnection study in the SPP interconnection queue, in Craighead County, Arkansas, connecting to SWPA.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-132
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SWPA
Connection point (POI)
Jonesboro - Independence 161 kV
Location
Craighead County, Arkansas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
December 2028

Location

Marker shows the centre of Craighead County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Craighead County