United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR + STORAGE Β· MISO

Solar + storage project J3110, Craighead County

Solar + storage project J3110, Craighead County is a 400 MW solar + storage request withdrawn in the MISO interconnection queue, in Craighead County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3110
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Powerline Road / 8POWERLN_RD% (338156) 500kV Substation
Location
Craighead County, Arkansas
Technology
Solar: 400 MW Β· Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
June 2026
Withdrawn
July 2025

Location

Marker shows the centre of Craighead County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Craighead County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem