Interconnection queue in PJM (Mid-Atlantic, Midwest) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,248140.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,248 requests · page 7 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Kensington Solar
Solar
145 MWPaused / redesign Columbiana, OHPJM Mar 2019target 2026
Kankakee Solar
Solar · AEUG Kankakee Solar, LLC
144 MWIn study Kankakee, ILPJM Feb 2020target 2021
Solar project AI2-037, King And Queen County
Solar
142 MWIn study King And Queen, VAPJM Jan 2023target 2027
Solar project AH2-349, Halifax County
Solar
142 MWIn study Halifax, VAPJM Mar 2022target 2025
Grover Hill Wind Project
Onshore wind
140 MWAgreement signed Paulding, OHPJM Sep 2018target 2026
Solar project AH1-188, Mingo County
Solar · Twisted Gun Solar, LLC
140 MWIn study Mingo, WVPJM Feb 2025target 2025
Solar project AG2-442, Charlotte County
Solar · Taro Solar LLC
140 MWIn study Charlotte, VAPJM Apr 2025target 2024
Battery storage project AI1-186, Shenandoah County
Battery storage
140 MWIn study Shenandoah, VAPJM Sep 2022target 2027
Battery storage project AH2-083, Caroline County
Battery storage
140 MWIn study Caroline, VAPJM Jan 2022target 2027
Battery storage project AI1-181, Venango County
Battery storage
140 MWIn study Venango, PAPJM Sep 2022target 2027
Woodridge Solar
Solar
138 MWAgreement signed Albemarle, VAPJM Feb 2019target 2027
Pulaski Energy Storage
Battery storage · Pulaski Energy Storage LLC
135 MWIn study Baltimore, MDPJM Feb 2025target 2025
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Solar project AG2-152, Pittsylvania County
Solar · Virginia Electric and Power Company
131 MWIn study Pittsylvania, VAPJM Mar 2025target 2024
Battery storage project AI1-183, Richmond County
Battery storage
130 MWIn study Richmond, VAPJM Sep 2022target 2027
Highland 3 Solar
Solar
130 MWAgreement signed Highland, OHPJM Sep 2019target 2030
Meadow Forge Solar Energy Center
Solar
130 MWPaused / redesign Delaware, INPJM Sep 2018target 2026
Red Brick Solar
Solar
130 MWAgreement signed Lunenburg, VAPJM Dec 2017target 2026
Battery storage project AI1-188, Erie County
Battery storage
130 MWIn study Erie, PAPJM Sep 2022target 2027
Battery storage project AH2-335, York County
Battery storage
130 MWIn study York, PAPJM Mar 2022target 2025
Nuclear project AH1-698, Will County
Nuclear · Constellation Energy Generation, LLC
130 MWIn study Will, ILPJM Apr 2025
South Branch Solar
Solar
130 MWAgreement signed Hancock, OHPJM Mar 2020target 2026
Harvey Solar I
Solar
128 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Solar + storage project AI1-080, Laporte County
Solar + storage
125 MWIn study Laporte, INPJM Jul 2022target 2026
Riverstart Solar Park II
Solar
125 MWAgreement signed Randolph, INPJM Mar 2019target 2027
Solar project AI1-145, Prince Edward County
Solar
125 MWIn study Prince Edward, VAPJM Sep 2022target 2026
Solar project AI1-124, Lunenburg County
Solar
125 MWIn study Lunenburg, VAPJM Sep 2022target 2026
Battery storage project AH2-084, Fauquier County
Battery storage
125 MWIn study Fauquier, VAPJM Jan 2022target 2027
Vinton Solar
Solar
125 MWAgreement signed Vinton, OHPJM Oct 2016target 2027
Quarter Horse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
125 MWAgreement signed Charlotte, VAPJM Sep 2020target 2031
Bluestem Solar
Solar · RWE Solar Development, LLC
125 MWIn study Laporte, INPJM Sep 2020target 2023
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Southern Virginia Solar
Solar
125 MWAgreement signed Pittsylvania, VAPJM Jul 2019target 2027
Battery storage project AI2-230, Caroline County
Battery storage
120 MWIn study Caroline, VAPJM Mar 2023target 2023
Border Basin
Solar
120 MWAgreement signed Hancock, OHPJM Sep 2018target 2026
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Battery storage project AI2-231, Prince William County
Battery storage
120 MWIn study Prince William, VAPJM Mar 2023target 2023
CC Solar I
Solar
120 MWPaused / redesign Caroline, VAPJM Sep 2018target 2025
Canal Road
Solar
120 MWAgreement signed Wayne, OHPJM Mar 2020target 2027
Rainbow Trout
Solar + storage
120 MWAgreement signed Tippecanoe, INPJM Sep 2020target 2028
Solar + storage project AI1-074, Jackson County
Solar + storage
120 MWIn study Jackson, OHPJM Jul 2022target 2027
Solar project AH2-345, Lorain County
Solar
120 MWIn study Lorain, OHPJM Mar 2022target 2025
New Road Storage
Battery storage
120 MWAgreement signed Loudoun, VAPJM Dec 2018target 2027
Tymochtee Solar
Solar
120 MWAgreement signed Wyandot, OHPJM Sep 2019target 2026
Chester Solar
Solar
120 MWAgreement signed Chesterfield, VAPJM Dec 2018target 2027
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023
Ridgeway Solar
Solar
120 MWAgreement signed Mckean, PAPJM Mar 2019target 2026
Solar + storage project AI1-174, Stephenson County
Solar + storage
118 MWIn study Stephenson, ILPJM Sep 2022target 2028
Sycamore Creek Solar
Solar
117 MWAgreement signed Crawford, OHPJM Dec 2016target 2025
Page 7 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)