United States › Grid › Interconnection queues › Virginia
SOLAR · PJMRed Brick Solar
Red Brick Solar is a 130 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Lunenburg County, Virginia, connecting to Dominion.
Queue statusConsented
- PlanningQueued Dec 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AD2-033
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Chase City-Lunenburg 115 kV
- Location
- Lunenburg County, Virginia
- Technology
- Solar: 130 MW
- Total requested
- 130 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 23 December 2017
- Proposed online date
- July 2026
Location
Marker shows the centre of Lunenburg County; the queue data does not give exact sites.
Other requests in Lunenburg County
- Solar project AI1-203, Lunenburg CountySolar · 300 MW · in study
- Solar project AI1-124, Lunenburg CountySolar · 125 MW · in study
- Solar project AG2-213, Lunenburg CountySolar · 80.0 MW · in study
- Solar project AG2-171, Lunenburg CountySolar · 60.0 MW · in study
- Solar project AI1-123, Lunenburg CountySolar · 59.0 MW · in study
- Solar project AH1-396, Lunenburg CountySolar · 11.9 MW · in study
- Solar project AG1-357, Lunenburg CountySolar · 200 MW · withdrawn
- Solar project AG2-633, Lunenburg CountySolar · 125 MW · withdrawn
- Solar + storage project AG1-347, Lunenburg CountySolar + storage · 100 MW · withdrawn
- Solar project AH1-656, Lunenburg CountySolar · 80.0 MW · withdrawn
- Victoria PV I, LLCSolar · 51.0 MW · withdrawn
- Solar project AF2-372, Lunenburg CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem