United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AF2-372, Lunenburg County
Solar project AF2-372, Lunenburg County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Lunenburg County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedAug 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-372
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Black Branch 34.5 kV
- Location
- Lunenburg County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- November 2021
- Withdrawn
- August 2020
Location
Marker shows the centre of Lunenburg County; the queue data does not give exact sites.
Other requests in Lunenburg County
- Red Brick SolarSolar Β· 130 MW Β· agreement signed
- Solar project AI1-203, Lunenburg CountySolar Β· 300 MW Β· in study
- Solar project AI1-124, Lunenburg CountySolar Β· 125 MW Β· in study
- Solar project AG2-213, Lunenburg CountySolar Β· 80.0 MW Β· in study
- Solar project AG2-171, Lunenburg CountySolar Β· 60.0 MW Β· in study
- Solar project AI1-123, Lunenburg CountySolar Β· 59.0 MW Β· in study
- Solar project AH1-396, Lunenburg CountySolar Β· 11.9 MW Β· in study
- Solar project AG1-357, Lunenburg CountySolar Β· 200 MW Β· withdrawn
- Solar project AG2-633, Lunenburg CountySolar Β· 125 MW Β· withdrawn
- Solar + storage project AG1-347, Lunenburg CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project AH1-656, Lunenburg CountySolar Β· 80.0 MW Β· withdrawn
- Victoria PV I, LLCSolar Β· 51.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem