Solar project AH1-656, Lunenburg County

Solar project AH1-656, Lunenburg County is a 80.0 MW solar request withdrawn in the PJM interconnection queue, in Lunenburg County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-656
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Gary 115kV
Location
Lunenburg County, Virginia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
23 September 2021
Proposed online date
December 2024
Withdrawn
June 2023

Location

Marker shows the centre of Lunenburg County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Lunenburg County