United States › Grid › Interconnection queues › Minnesota
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Minnesota — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project J1228, Faribault County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1473, Chisago County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project J3778, Otter Tail County Battery storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project H046, Jackson County Onshore wind |
100 MW | Withdrawn / abandoned |
| Other project G245, Mower County Other |
100 MW | Withdrawn / abandoned |
| Solar project J1110, Mower County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project G843, Otter Tail County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project G491, Pipestone County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J014, Stearns County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project J1568, Renville County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J547, Sherburne County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project G910, Mower County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project G911, Mower County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project G912, Mower County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J198, Lyon County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Solar project J2420, Faribault County Solar |
95.0 MW | Withdrawn / abandoned |
| Solar project J770, Renville County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar project J2286, Polk County Solar |
90.0 MW | Withdrawn / abandoned |
| Solar project J3278, Swift County Solar |
90.0 MW | Withdrawn / abandoned |
| Onshore wind project J3237, Itasca County Onshore wind |
86.0 MW | Withdrawn / abandoned |
| Onshore wind project H070, Renville County Onshore wind |
85.0 MW | Withdrawn / abandoned |
| Onshore wind project G759, Cottonwood County Onshore wind |
84.8 MW | Withdrawn / abandoned |
| Onshore wind project G875, Kittson County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project J1140, Benton County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project J624, Yellow Medicine County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project J951, Kittson County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project J1645, Renville County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project G893, Rock County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project J3397, Rock County Solar |
80.0 MW | Withdrawn / abandoned |
| Other project G235, Washington County Other |
79.0 MW | Withdrawn / abandoned |
| Onshore wind project G828, Blue Earth County Onshore wind |
76.0 MW | Withdrawn / abandoned |
| Onshore wind project G509, St. Louis County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project H044, Watonwan County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project J243, Jackson County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar project J1597, Wadena County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project H066, Rice County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Solar + storage project J2760, Hubbard County Solar + storage |
68.0 MW | Withdrawn / abandoned |
| Onshore wind project J2054, Freeborn County Onshore wind |
67.0 MW | Withdrawn / abandoned |
| Onshore wind project G239, Dodge County Onshore wind |
63.0 MW | Withdrawn / abandoned |
| Solar project J1212, Murray County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project J1941, Polk County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project J3217, Cottonwood County Solar |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project J287, Nobles County Onshore wind |
56.7 MW | Withdrawn / abandoned |
| Onshore wind project G932, Swift County Onshore wind |
56.0 MW | Withdrawn / abandoned |
| Onshore wind project H069, Waseca County Onshore wind |
55.0 MW | Withdrawn / abandoned |
| Gas project G337, Waseca County Gas |
55.0 MW | Withdrawn / abandoned |
| Gas project G336, Rice County Gas |
55.0 MW | Withdrawn / abandoned |
| Onshore wind project H052, Brown County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Battery storage project J1496, Olmsted County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project H045, Cottonwood County Onshore wind |
50.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)476 · 79.8 GW
- West (non-ISO utilities)4 · 405 MW
- SPP (Southwest Power Pool)2 · 323 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)