United States › Grid › Interconnection queues › Minnesota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown48280.5 GW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

482 requests · page 6 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1228, Faribault County
Solar
100 MWWithdrawn / abandoned Faribault, MNMISO Apr 2019target 2023
Solar project J1473, Chisago County
Solar
100 MWWithdrawn / abandoned Chisago, MNMISO Apr 2019target 2022
Battery storage project J3778, Otter Tail County
Battery storage
100 MWWithdrawn / abandoned Otter Tail, MNMISO Apr 2024target 2028
Onshore wind project H046, Jackson County
Onshore wind
100 MWWithdrawn / abandoned Jackson, MNMISO Jun 2008target 2011
Other project G245, Mower County
Other
100 MWWithdrawn / abandoned Mower, MNMISO Aug 2002target 2002
Solar project J1110, Mower County
Solar
100 MWWithdrawn / abandoned Mower, MNMISO Mar 2018target 2021
Onshore wind project G843, Otter Tail County
Onshore wind
100 MWWithdrawn / abandoned Otter Tail, MNMISO Aug 2007target 2010
Onshore wind project G491, Pipestone County
Onshore wind
100 MWWithdrawn / abandoned Pipestone, MNMISO Dec 2004target 2010
Onshore wind project J014, Stearns County
Onshore wind
100 MWWithdrawn / abandoned Stearns, MNMISO Jan 2009target 2010
Solar project J1568, Renville County
Solar
100 MWWithdrawn / abandoned Renville, MNMISO Jun 2020target 2023
Solar project J547, Sherburne County
Solar
100 MWWithdrawn / abandoned Sherburne, MNMISO Mar 2016target 2018
Onshore wind project G910, Mower County
Onshore wind
99.0 MWWithdrawn / abandoned Mower, MNMISO Nov 2007target 2010
Onshore wind project G911, Mower County
Onshore wind
99.0 MWWithdrawn / abandoned Mower, MNMISO Nov 2007target 2010
Onshore wind project G912, Mower County
Onshore wind
99.0 MWWithdrawn / abandoned Mower, MNMISO Nov 2007target 2010
Onshore wind project J198, Lyon County
Onshore wind
99.0 MWWithdrawn / abandoned Lyon, MNMISO Feb 2011target 2012
Solar project J2420, Faribault County
Solar
95.0 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Solar project J770, Renville County
Solar
90.0 MWWithdrawn / abandoned Renville, MNMISO Nov 2016target 2019
Solar project J2286, Polk County
Solar
90.0 MWWithdrawn / abandoned Polk, MNMISO Jul 2021target 2026
Solar project J3278, Swift County
Solar
90.0 MWWithdrawn / abandoned Swift, MNMISO Apr 2024target 2028
Onshore wind project J3237, Itasca County
Onshore wind
86.0 MWWithdrawn / abandoned Itasca, MNMISO Apr 2024target 2028
Onshore wind project H070, Renville County
Onshore wind
85.0 MWWithdrawn / abandoned Renville, MNMISO Jun 2008target 2010
Onshore wind project G759, Cottonwood County
Onshore wind
84.8 MWWithdrawn / abandoned Cottonwood, MNMISO Jan 2007
Onshore wind project G875, Kittson County
Onshore wind
80.0 MWWithdrawn / abandoned Kittson, MNMISO Oct 2007target 2015
Solar project J1140, Benton County
Solar
80.0 MWWithdrawn / abandoned Benton, MNMISO Mar 2018target 2020
Solar project J624, Yellow Medicine County
Solar
80.0 MWWithdrawn / abandoned Yellow Medicine, MNMISO May 2016target 2018
Onshore wind project J951, Kittson County
Onshore wind
80.0 MWWithdrawn / abandoned Kittson, MNMISO Feb 2018target 2018
Solar project J1645, Renville County
Solar
80.0 MWWithdrawn / abandoned Renville, MNMISO Jun 2020target 2023
Onshore wind project G893, Rock County
Onshore wind
80.0 MWWithdrawn / abandoned Rock, MNMISO Oct 2007target 2010
Solar project J3397, Rock County
Solar
80.0 MWWithdrawn / abandoned Rock, MNMISO Mar 2024target 2026
Other project G235, Washington County
Other
79.0 MWWithdrawn / abandoned Washington, MNMISO Jan 2002target 2003
Onshore wind project G828, Blue Earth County
Onshore wind
76.0 MWWithdrawn / abandoned Blue Earth, MNMISO Jul 2007target 2010
Onshore wind project G509, St. Louis County
Onshore wind
75.0 MWWithdrawn / abandoned St. Louis, MNMISO Mar 2005target 2006
Onshore wind project H044, Watonwan County
Onshore wind
75.0 MWWithdrawn / abandoned Watonwan, MNMISO Jun 2008target 2011
Onshore wind project J243, Jackson County
Onshore wind
75.0 MWWithdrawn / abandoned Jackson, MNMISO May 2012target 2015
Solar project J1597, Wadena County
Solar
75.0 MWWithdrawn / abandoned Wadena, MNMISO Jun 2020target 2023
Onshore wind project H066, Rice County
Onshore wind
70.0 MWWithdrawn / abandoned Rice, MNMISO Jun 2008target 2010
Solar + storage project J2760, Hubbard County
Solar + storage
68.0 MWWithdrawn / abandoned Hubbard, MNMISO Sep 2022target 2027
Onshore wind project J2054, Freeborn County
Onshore wind
67.0 MWWithdrawn / abandoned Freeborn, MNMISO Aug 2021target 2024
Onshore wind project G239, Dodge County
Onshore wind
63.0 MWWithdrawn / abandoned Dodge, MNMISO Jun 2002target 2008
Solar project J1212, Murray County
Solar
60.0 MWWithdrawn / abandoned Murray, MNMISO Apr 2019target 2023
Solar project J1941, Polk County
Solar
60.0 MWWithdrawn / abandoned Polk, MNMISO Aug 2021target 2026
Solar project J3217, Cottonwood County
Solar
60.0 MWWithdrawn / abandoned Cottonwood, MNMISO Sep 2022target 2026
Onshore wind project J287, Nobles County
Onshore wind
56.7 MWWithdrawn / abandoned Nobles, MNMISO Jun 2013target 2015
Onshore wind project G932, Swift County
Onshore wind
56.0 MWWithdrawn / abandoned Swift, MNMISO Dec 2007target 2012
Onshore wind project H069, Waseca County
Onshore wind
55.0 MWWithdrawn / abandoned Waseca, MNMISO Jun 2008target 2010
Gas project G337, Waseca County
Gas
55.0 MWWithdrawn / abandoned Waseca, MNMISO Apr 2003target 2005
Gas project G336, Rice County
Gas
55.0 MWWithdrawn / abandoned Rice, MNMISO Apr 2003target 2005
Onshore wind project H052, Brown County
Onshore wind
50.0 MWWithdrawn / abandoned Brown, MNMISO Jun 2008target 2011
Battery storage project J1496, Olmsted County
Battery storage
50.0 MWWithdrawn / abandoned Olmsted, MNMISO Jun 2020target 2023
Onshore wind project H045, Cottonwood County
Onshore wind
50.0 MWWithdrawn / abandoned Cottonwood, MNMISO Jun 2008target 2011
Page 6 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)