ONSHORE WIND Β· MISO

Onshore wind project G828, Blue Earth County

Onshore wind project G828, Blue Earth County is a 76.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Blue Earth County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2007 (completed)
  2. Withdrawn / abandonedJan 2011 (project stopped here)
  3. ConsentedJan 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G828
Grid region
MISO (Midcontinent)
Connection point (POI)
345 kV line near Wilmarth substation
Location
Blue Earth County, Minnesota
Technology
Wind: 76.0 MW
Total requested
76.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
16 July 2007
Agreement signed
5 January 2011
Proposed online date
August 2010
Withdrawn
January 2011

Location

Marker shows the centre of Blue Earth County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Blue Earth County